IESCO New Meter Connection

Getting a new electricity connection with Islamabad Electric Supply Company (IESCO) is an important step for any new homeowner or business in the region. IESCO provides electricity to Islamabad Capital Territory and surrounding areas, ensuring reliable and efficient power supply. Details about IESCO New Connection are discussed below.

IESCO New Connection
IESCO New Connection

Check and Download Your New IESCO Bill Here.

Requirements For IESCO New Meter Connection

List of required documents for new IESCO meter connection are as-follows;

  • Attested copy of CNIC of the applicant
  • Attested copy of witness CNIC
  • Proof of ownership or tenancy (property paper or rental agreement)
  • No Objection Certificate (NOC) if applicable
  • Copy of neighbor’s IESCO Bill

Process For New IESCO Connection

The step-by-step process for new meter connection of IESCO are as-follows;

  • Visit the “ENC” site.
  • Click on “Apply New Connection”.
  • Fill the required fields on the form.
  • Submit the form after filling it out.
  • Print out a copy of the online application form.
  • Attach all the required documents with the form.
  • Submit it to the nearest IESCO office.
  • When your documents are verified, you will be sent a Demand Notice.
  • Pay the Demand Notice to the nearest bank.
  • Make a copy of the paid Demand Notice.
  • Send the copy to the IESCO office.
  • When your Demand Payment Notice is verified, a new connection will be given.

IESCO New Electricity Connection Fee

The charges you have to pay for your new electricity connection are listed below in details;

Single Phase Meter

Sr.NoLength Of ServiceCost
1Length of service line upto 20 meters.Rs. 8,500/-
2Length of service line above 20 and upto 30 meters.Rs. 10,500/-
3Length of service line above 30 and upto 40 meters.Rs. 11,500/-
4Length of service line above 40 meters and upto and including 100 meters with one span LT with Ant Conductor and one Pole (Excluding connections under Housing Societies).Rs. 11,000 + 800 per meter above 40 meters
5
Length of service line above 100 meters and upto and including 160 meters with two span LT with Ant Conductor and two Poles (Excluding connections under Housing Societies).
Rs. 60,000 + 1000 per meter above 100 meters
IESCO New Single Phase Meter Fee

Three Phase Meter

Sr.NoLength Of ServiceCost
1Service line upto 20 meters.Rs. 36,500/-
2Service line upto 30 meters.Rs. 43,000/-
3Service line upto 40 meters.Rs. 50,000/-
4For consumer having service lines above 40 meters, the actual cost of LT Pole, or and allied material is to be recovered from the consumers as per the latest / store rates / price bulletin issued by Chief Engineer (MM) IESCO.
IESCO New Three Phase Meter Fee

Required Time For IESCO New Electricity Connection

Sr.NoDescriptionDays
1For supply at voltage level up to 400V and load up to 15KW30
2For supply at voltage level up to 400V and load above 15KW but not exceeding 70KW53
3For supply at voltage level up to 400V and load up to 70KW but not exceeding 500KW73
4For supply at voltage level up to 400V and load up to 500KW but not exceeding 5000KW106
5For supply at voltage level 66KV and above for all loads496
Required Time For IESCO New Connection

FAQ’s

How long does it take to get a new connection from IESCO?

The timeline for obtaining a new connection varies based on several factors, but it generally takes a few weeks from application submission to meter installation.

What documents are required for a new connection?

You will need proof of ownership, identification documents, and technical requirements like load assessment forms.

Can I apply for a new connection online?

Yes, IESCO offers an online application portal for new connections, visit “IESCO New Connection” for more details.

What are the fees associated with a new connection?

Fees vary based on the type of connection and load requirements. Visit “IESCO New Connection” for detailed information.

What happens during the site inspection?

During the site inspection, IESCO officials will verify the details provided in your application and ensure that the site meets all technical requirements.

How can I contact IESCO customer support?

IESCO customer support can be reached through their helpline No 118 or SMS on 8118, or in-person visits to their offices. Contact details are available on the “IESCO Helpline”.